Northborough Fire Station Project
To submit questions or comments to the Fire Station Building click on the link below. You question/comment will be discussed at the next scheduled committee meeting and a reply will be drafted.
Questions submitted will be reviewed by the board and discussed at our next scheduled meeting
Budget Tracking
As we continue work on this project we want you to be able to see an overview of the changes to the bottom line of the proposed budget. Below you will see the initial budget that was developed based on the schematic design and the most recent budget after our first review.
Project Budget Development High/Low Cost Range | |||||
---|---|---|---|---|---|
Total Project Cost | Low Range | High Range | |||
2/28/2024 Schematic Design Estimate | $42,969,700 | $49,906,000 | |||
3/27/2024 | $39,749,400 | $45,229,600 | |||
4//15/2024 (Committee Approved Geothermal Option) | $42,895,300 | $45,697,200 | |||
Geothermal State and Federal rebates | $1,958,564 | $1,958,564 | |||
Total minus rebates | $40,936,736 | $43,738,636 | |||
Design Development Cost Estimate Expected Late May |
DESIGN DEVELOPMENT PHASE | 2/29/2024- 5/29/2024 | |
Conservation Commission Zoom | 6:00 PM | 5/13/2024 |
Planning Board Zoom | 6:00 PM | 5/21/2024 |
FSBC | 6:30 PM | 5/29/2024 |
Design Development Cost Estimate | 5/3/2024-5/24/2024 | |
FSBC Design Development Cost Estimate Presented | 6:30 PM | 5/22/2024 |
CONSTRUCTION DOCUMENT PHASE | 5/30/2024-9/20/2024 | |
Prequalification Process | July | |
FSBC Construction Document Review (anticipate 50% completed) | 6:30 PM | 7/24/2024 |
Construction Document Cost Estimate | 7/26/2024-8/16/2024 | |
Deadline to notify the Secretary of State for Ballot Vote | 8/7/2024 | |
FSBC Construction Document Review (anticipate 75% completed) | 6:30 PM | 8/21/2024 |
Construction Documents issued for Bid | 9/20/2024 | |
BIDDING PHASE | 9/23/2024-10/25/2024 | |
Deadline for Selectboard to place project on the ballot | 9/24/2024 | |
Bidding | 9/23/2024-10/25/2024 | |
TOWN MEETING | FALL 2024 | |
Special Town Meeting | No later than 10/14/2024 | |
Debt Exclusion Vote | 11/5/2024 | |
Contract Signed with General Contractor | 11/6/2024 | |
CONSTRUCTION PHASE | JANUARY 2025- MARCH 2026 | |
Ground Breaking | Beginning of 2025 | |
Estimated Construction Phase of 14 Months | 1/1/2025- 3/30/2026 |
Past Meetings and Presentations!
Past meetings on YouTube | Click here to view our past meetings |
Chief Presentation to Selectboard 11/06/2023 | Chief's Selectboard Meeting Presentation |
Joint FSBC, Design Review, and MPIC 12/14/2023 | Presentation for Joint FSBC, Design Review and MPIC |
FSBC Meeting 1/10/2024 Presentation | FSBC 01/10/2024 Presentation |
Public Input Meeting 1/17/2024 | Public Input Session 01/17/2024 Presentation |
Design Review Committee | Presentation Meeting Link |
FSBC 1/31/2024 | FSBC 01/31/2024 Presentation |
FSBC 2/14/2024 | FSBC 02/14/2024 Presentation |
Design Review 2/29/2024 | Meeting Link |
FSBC Selectboard 3/11/2024 | Presentation |
FSBC/Design Review 3/20/2024 | Exterior Design Options |
ZBA 3/26/2024 | Meeting Link |
FSBC 03/27/2024 | Presentation |
FSBC 4/3/2024 | |
Design Review 4/16/2024 | Meeting Link |
Planning Board 4/16/2024 | Meeting Link |
FSBC 5/01/2024 | |
Community Information session 5/8/2024 | Presentation |
Design Review Committee 5/9/2024 | Meeting Link |
Previous Meeting Minutes | Minutes |
Limited Space for Apparatus
Mechanic's Room Protective Gear Exposed to UV light and no ventilation Hose Tower used for Storage
Dive Equip Stored in Utility Room Training/Meeting Room & Gym Limited Office Space