Rice Ave Culvert Replacement Project - Temporary Detour Plan (7/25/19 - 8/27/19)
Attachments:
Attachment NameAttachment SizeAttachment Date
Size: 553K
Last Updated: 2019/7/23
Northborough Department of Public Works
 
NOTICE

Rice Avenue will be closed for culvert replacement near the intersection with Chapin Street.  All traffic approaching from the North (Colburn St.) will be detoured down Chapin Street, through Colburn Street and onto Hudson Street.  Only local traffic will be allowed from the South (Allen St.).  Through traffic will be detoured down Allen Street and onto Hudson Street.  Work is scheduled to begin July 25th and end no later than August 27th in advance of the start of the school year.